8
Hazards
5
Unit tasks
7
Related laws
Criminal 4
Full risk assessment
Unit taskHazard / CauseCurrent controlsRisk (F×S)ControlsAfterLegal
Lift plan & pre-lift inspection
Crane overload due to underestimated load weight — structural failure
No accurate load weight calculated; rated capacity not verified
Falling Objects
Visual capacity placard8· Medium
4×2
  • EngineeringInstall load cell (rated capacity limiter) that prevents lift if weight exceeds 90% SWL
  • AdministrativeMandatory lift plan with load weight certification for all critical lifts (>75% SWL)
4· Medium
제168조
변형되어 있는 훅ㆍ샤클 등의 사용금지 등
Criminal
Lift plan & pre-lift inspection
Crane wire rope failure — load drops on workers
Wire rope worn beyond retirement criteria; no pre-shift inspection
Struck-by / Impact
Annual crane inspection certificate8· Medium
2×4
  • EngineeringReplace wire rope at 10% broken wires per lay length; use synthetic slings where appropriate
  • AdministrativePre-shift visual inspection of all wire ropes by crane operator before use; document and record
3· Low
제146조
크레인 작업 시의 조치
Criminal
Rigging & load securing
Musculoskeletal injury during manual rigging attachment to heavy load
Awkward posture and heavy sling weight when rigging in confined area
Musculoskeletal Disorder
General manual-handling guidance12· High
3×4
  • EngineeringProvide rigging aids (hook positioners, magnetic attachment aids) to reduce manual effort
  • AdministrativeTwo-person rigging team for loads over 25 kg; ergonomic task briefing before rigging
3· Low
제146조
크레인 작업 시의 조치
Criminal
Rigging & load securing
Load falls during initial lift due to inadequate rigging
Sling angle too acute; single sling point for off-centre load; sling damaged
Falling Objects
Rigger competency training10· High
2×5
  • AdministrativeInspect all slings before use; use rated slings at correct angle (>60°); load-test rig before full lift
  • EngineeringRequire certified rigger to sign rigging plan for all critical lifts
4· Medium
제134조
방호장치의 조정
Criminal
Lift, swing & travel
Swinging load strikes worker or structure during crane travel
Load pendulum effect from sudden travel or swing; no tag lines; no exclusion zone
Struck-by / Impact
Operator experience6· Medium
3×2
  • EngineeringInstall anti-sway system on crane; use tag lines (minimum 2) for all loads
  • AdministrativeEstablish and enforce exclusion zone equal to load height + 1 m radius; signal person controls all movements
2· Low
Art. 171
전도 등의 방지
Criminal
Lift, swing & travel
Crane boom or wire rope contacts overhead power line
Crane working near overhead lines; no minimum clearance maintained
Electrical Shock
Awareness of overhead lines10· High
2×5
  • EngineeringInstall proximity warning device that alerts operator when within 3 m of power lines
  • AdministrativeContact utility company to de-energise or re-route lines; maintain 3 m minimum clearance
4· Medium
Art. 171
전도 등의 방지
Criminal
Load lowering & placement
Load swings or tips during lowering and falls on worker
Load off-balance when lowered; ground worker in load zone
Falling Objects
Signal person guiding load9· High
3×3
  • AdministrativeAll workers out of load swing zone during lowering; ground workers use tag lines from safe distance
  • EngineeringControlled-lowering device limits descent speed; load must be balanced before lowering begins
2· Low
제134조
방호장치의 조정
Criminal
Rigging removal & post-lift
Sling or rigging accessory falls from height when detached
Rigger releases sling without securing it first; sling falls from hook
Falling Objects
Verbal warning6· Medium
3×2
  • AdministrativeAttach securing line to sling before releasing from load; never release above unprotected workers
  • EngineeringUse latch-type hooks that retain rigging until manually released by rigger
2· Low
제134조
방호장치의 조정
Criminal
Legal compliance (OSH rules)
Art. 132Crane Inspection Requirements
CriminalMust-check
Art. 133Rated Capacity Limiter
CriminalMust-check
Art. 134Signal Person Requirements
CriminalMust-check
Art. 135Exclusion Zone During Lifts
CriminalMust-check
Art. 93PPE Provision
Must-check
Art. 136Lift Plan Requirements
Art. 137Wire Rope Maintenance
Grounding real accidents

Crane boom contacted a 154 kV overhead power line during a lift; operator received severe electrical burns.

⚠ Crane boom contacts energised overhead line

Load swung out of control when crane operator slewed too quickly; load struck and fatally injured a worker.

⚠ Uncontrolled load pendulum strikes worker

Wire rope parted during lift — post-incident inspection found 23% of wires broken in one lay length.

⚠ Wire rope overdue for retirement — in-service failure

Overloaded mobile crane tipped over; counterweight crushed two workers on the ground.

⚠ Crane overload and tip-over